New Hamad international airport

Project name     New Hamad international Airport 
Customer  Anel
End User  NDIA
Segment PMCS
Country  QATAR 
Duration 2013 - 2018

Scope :

Design,Supply,Engineering, configuration,programming and commissioning of SCADA & power Managmement System (PME) for Medium Voltage (MV) SWGR & Low Voltage (LV) SWGR inside the Airport.

Solution Description :

Two Control rooms each one have redundant servers & Two Workstations to Monitor & Control the following :

  • Qty (12) LV SWGR Panel Through QTy (6) DCONC Control panel in terminal Building A & B
  • Qty (12) LV SWGR Panel Through QTy (6) DCONC Control panel in terminal Building C
  • Qty (12) LV SWGR Panel Through QTy (6) DCONC Control panel in Emiri terminal
  • Qty (4) LV SWGR Panel Through QTy (2) DCONC Control panel in car park & mosque 
  • Qty (4) LV SWGR Panel Through QTy (1) DCONC  Control panel in CP50
  • Qty (4) LV SWGR Panel Through QTy (1) DCONC  Control panel in CP51
  • Qty (1100 ) Power Meter Installed inside LV & sub LV Panels
  • Integration with exist Siemens SCADA & BMS System